Significant progress has been made in the hydro-mechanical works at the headworks of the project. Gravel flushing arrangements, gate frames, gates, and transition pipes have been successfully installed. Gate frame installations in the settling basin, as well as the fabrication and erection of transition and sand flushing pipes, are completed. Additionally, various gate frames and lifts have been fabricated, with trash rack installation currently underway.