Significant Progress in Penstock Alignment: Excavation, Saddle Construction, and Protection Works Advancing

The penstock alignment project is progressing steadily with excavation completed in multiple sections, including AB33-35, AB39-45, and AB46-57. Debris clearing is ongoing in key areas to facilitate further work. Saddle construction has been completed in sections AB46-47, AB48-57, and AB39-45, while work continues in AB47-48 and AB34-39. Additionally, five anchor blocks have been concreted, with three more scheduled for immediate construction. Alignment protection works, including gabion installation, are 30% complete, showcasing steady advancements in the project.