January 8, 2025

Headwork 32% completed

January 7, 2025

Penstock Alignment 800 m completed

January 6, 2025

Headrace Alignment 1250 m completed

November 30, 2024

Headrace Alignment Progress: 925m of Pipes Erected, Welding Advancing Steadily

October 2, 2024

Corporate Social Works: Road Upgrades Completed and Community Development Initiatives Progressing

August 2, 2024

Hydro-Mechanical Works at Headworks: Key Installations and Fabrication Completed

June 2, 2024

Headworks of Doodhpokhari Chepe Hydropower Project Achieves 32% Completion with Key Structures Progressing

April 2, 2024

Significant Progress in Penstock Alignment: Excavation, Saddle Construction, and Protection Works Advancing

December 6, 2023

Camp Facilities Construction ongoing at Intake Area

December 4, 2023

Construction Power Works from Powerhouse to Intake ongoing

December 1, 2023

Construction of Bay at Kirtipur Substation, Pokhara Grid, Lamjung

September 13, 2023

Transmission Line: Completion of 33 kV Double Circuit Transmission

March 30, 2023

Camp Facilities construction at Powerhouse area updated.

March 28, 2023

Financial Closure with Rastriya Banijya Bank, Corporate has been completed on 2nd Feburary 2023.

April 27, 2022

Track opening from Powerhouse to Intake has been Completed.

December 9, 2021

Installation of Transformer for Power construction is done.

December 9, 2021

Camp Facilities construction at Powerhouse area completed on 2078/06/15.

July 30, 2021

Construction Power work from Olang to Tal Bagar is ongoing from 2078/04/05.

July 30, 2021

Camphouse Construction is ongoing from 2078/01/20.

March 31, 2021

Track Opening on a process to Powerhouse (Tal Bagar).

November 12, 2020

Road Track Opening & Upgrading

November 10, 2020

COVID – 19 Information